Funding Agreement for Tendring Community Regeneration Partnership
Is a Key Decision:
Yes
Stakeholder Involvement

Tendring District Council; ECC Members; ECC Legal; ECC Finance Business Partner; ECC Capital Investment and Delivery; ECC Highways; ECC Passenger Transport Team; Place Services; ACL (Business Operations)

Public not consulted on funding agreement, but consultation activities relevant to the individual projects are outlined in the ECIA ECC Infrastructure Delivery Board; ECC Finance Oversight Board.

Date on which, or period within which, we expect the decision to be taken
Mon 1 Sep 2025
Decision Date Notes

Decision added to CMIS: Tuesday 31st December 2024

Key Decisions must be on the Forward Plan for 28-days, the 28-day period ends: Tuesday 28th January 2025. 

Decision is expected to be taken in February 2025. 

Key decisions are automatically rolled over to the next month, decision rolled over.

Forward Plan number is no longer, FP/319/12/24, due to a duplication, this has been changed to FP/023/01/25.

Decision published: Wednesday 27th August 2025

Decision subject to three-day call-in, call-in ends: Monday 1st September 2025. 

Cabinet Member
Housing, Planning and Regeneration
Include Item on Forward Plan:
No
Lead Officer

Anna Watson, Localities Lead, 

anna.watson@essex.gov.uk

Background Papers:
Cabinet Member Action; Report Funding Agreement; OBC (Tendring Levelling Up Partnership); ECIA; Community Regeneration Partnership Background.
Decision Type:
Portfolio
Decision Maker Role:
Housing, Planning and Regeneration
Is the Decision Maker Aware of the Decision:
Yes
Is the Head of Services Aware of the Decision:
Yes
Is Decision Exempt from Call-in
No

Additional Information

Details

2. Recommendations

Cabinet Member for Housing, Planning and Regeneration:

2.1 Agree to enter into a Funding Agreement in the form at Appendix A) with Tendring District Council (TDC) to the value of £1.73m to enable delivery of three ECC-led Community Regeneration Projects, covering Clacton West and Jaywick Sands. The total estimated cost of the projects identified below is £1.73m, this is both Capital and Revenue expenditure due to be incurred between April 2024 and November 2027:

Improved Bus Infrastructure for works to around 32 bus stops within Clacton Jaywick Sands (total estimated capital cost of £230,000)
Improved Public Realm to enhance way finding between Clacton seafront and town centre, including new street furniture (£1.3m) 
Fit out the Adult Community Learning (ACL) skills centre in the Clacton Hub, providing ten classrooms space and equipment for vocational courses including hospitality, health and social care (£200,000). 

2.2 The projects will be delivered through grant funding from the Ministry of Housing and Local Government (MHCLG), as part of the Tendring Community Regeneration Partnership (CRP) and Tendring District Council (TDC) are the accountable body.

2.3 Agree that the Director for Sustainable Growth in consultation with the?Section 151 Officer, the Director, Legal and Assurance and the Cabinet Member for Housing, Planning and Regeneration, is authorised to procure contracts for the works and award contracts if he is satisfied that sufficient funding is in place.   

Cabinet Member with responsibility for Finance:

2.4 Agree to the addition of £1.53m to the ECC capital programme as outlined in the financial section to enable delivery of the schemes outlined above. The addition is to be fully funded from the capital grant due to be received by TDC via a funding agreement in relation to Community Regeneration Partnership Fund A. 

Decision Criteria

This Decision does not contain any decision criteria records.

Divisions

This Decision does not contain any Division records.

Topics

This Decision does not contain any Topic records

Overview and Scrutiny

This Decision does not contain any Overview and Scrutiny records.

This section displays the history of the Decision.

Decision History

Date & Time CreatedUser Full NameStatus DescriptionDetails
123
 Page 1 of 3, items 1 to 10 of 29.
31/12/2024 11:40:50Maise RileyBusiness Item Created 
31/12/2024 11:53:29Maise RileyReport AddedDocument ID 246610: FP-319-12-24
31/12/2024 11:54:19Maise RileyStatus ChangedDecision Proposed [2]
31/12/2024 12:01:36Maise RileyGeneral Details Edited 
03/02/2025 13:16:06Maise RileyGeneral Details Edited 
03/02/2025 16:04:47Maise RileyGeneral Details Edited 
03/02/2025 16:37:14Maise RileyGeneral Details Edited 
03/02/2025 16:38:06Maise RileyGeneral Details Edited 
05/02/2025 14:16:08Maise RileyGeneral Details Edited 
03/03/2025 15:49:40Maise RileyGeneral Details Edited 

Approval/Comments

No history found.
Print this page