Clacton Hub Project Procurement
Is a Key Decision:
Yes
Stakeholder Involvement

The Clacton Hub project undertook public consultation in Summer 2024, which informed the final designs that were submitted for planning approval in November 2024. The planning application submission was also subject to statutory consultation in December 2024/January 2025.

Date on which, or period within which, we expect the decision to be taken
Fri 12 Sep 2025
Decision Date Notes

Added to the Forward Plan 24/07/2025.

 A key decision must be on the plan for 28-days, the 28-day period ends: 21 August 2025.

This decision is to be taken at the 9 September 2025 Cabinet meeting.  

Decision taken at the September Cabinet meeting. Decision is subject to three-day call-in, call-in ends: Friday 12th September 2025

Cabinet Member
Housing, Planning and Regeneration
Include Item on Forward Plan:
No
Lead Officer

Andy Burgess – Director Sustainable Growth

Background Papers:

Reports to Follow.

Cabinet Report, Equality Comprehensive Impact Assessment, Background Paper: 'Clacton Hub – Levelling Up Fund Project Approvals'.

Decision Type:
Committee
Decision Maker:
Cabinet
Is the Decision Maker Aware of the Decision:
Yes
Is the Head of Services Aware of the Decision:
Yes
Is Decision Exempt from Call-in
No

Additional Information

Details
To approve the use of the Essex Construction Framework 3 (Lot 3) via a 2-stage tender process to procure a contractor for the construction of the Clacton Hub project that is part of the wider Clacton Civic Quarter programme part-funded by the Government's Levelling Up Fund (£3.1m), which ECC is receiving from Tendring District Council as the accountable body in accordance with the terms of the funding agreement approved in January 2024. Additionally, to delegate authority to the Executive Director for People, 
Policy, Economy & Public Health for the awarding at the initial PCSA (Pre-construction services agreement)/design stage and for awarding the contract on the basis that the successful tender is in line with the expected budget for the delivery of this project. 

Decision Criteria

This Decision does not contain any decision criteria records.

Divisions

This Decision does not contain any Division records.

Topics

This Decision does not contain any Topic records

Overview and Scrutiny

This Decision does not contain any Overview and Scrutiny records.

This section allows you to view the reports for the Decision.

This section displays the history of the Decision.

Decision History

Date & Time CreatedUser Full NameStatus DescriptionDetails
12
 Page 1 of 2, items 1 to 10 of 15.
24/07/2025 15:45:15Chloe O'MalleyBusiness Item Created 
24/07/2025 15:45:15Chloe O'MalleyCommittee AddedCabinet
24/07/2025 15:45:15Chloe O'MalleyMeeting Added09/09/2025 10:15AM
24/07/2025 15:46:51Chloe O'MalleyReport AddedDocument ID 258205: FP-162-07-25
24/07/2025 15:47:00Chloe O'MalleyStatus ChangedDecision Proposed [2]
24/07/2025 17:13:22Chloe O'MalleyGeneral Details Edited 
04/08/2025 12:44:45Maise RileyGeneral Details Edited 
04/08/2025 13:59:00Maise RileyGeneral Details Edited 
04/08/2025 14:01:44Maise RileyGeneral Details Edited 
09/09/2025 16:07:25Maise RileyGeneral Details Edited 

Approval/Comments

No history found.
Print this page