This section allows you to view the general details of a Decision
Details
Status:
Decision Confirmed
Title:
Procurement of Bus Infrastructure Supplier (Flags, Poles, Timetable Frames and Printed Timetable Posting)
Stakeholder Involvement
The ECIA indicates no consultation is required.
Date on which, or period within which, we expect the decision to be taken
Fri 26 Sep 2025
Decision Date Notes
Added to the Forward Plan 24/07/2025.
A key decision must be on the plan for 28-days, the 28-day period ends: 21 August 2025.
Decision automatically rolled over to the next month.
Decision published: Tuesday 23rd September 2025
Decision subject to three-day call-in, call-in ends: Friday 26th September 2025
Cabinet Member
Highways & Transportation
Include Item on Forward Plan:
No
Background Papers:
CMA ECIA
No background papers.
Decision Maker Role:
Highways, Infrastructure and Sustainable Transport
Is the Decision Maker Aware of the Decision:
Yes
Is the Head of Services Aware of the Decision:
Yes
Is Decision Exempt from Call-in
No
Additional Information
Details
A CMA requesting permission to procure a provider through an open procurement for the supply, installation and maintenance of Bus Infrastructure, including the posting of printed timetables, for an 8-year, and 3-month term, with the option to extend for a further 5 years. The estimated contract value for the initial 8 years and 3-month term is £2.5m.
2 Recommendations
2.1 To agree to procure a provider through an open procurement for the supply, installation and maintenance of Bus Infrastructure, including the posting of printed timetables, for an 8-year, and 3-month term, with the option to extend for a further 5 years. The contract value for the initial 8 years and 3-month term is £2.5m.
2.2 To note that the procurement will be divided into two lots which cover all of administrational Essex so it can be awarded to multiple or one provider depending on outcome. To reduce costs combined bids will be encouraged.
2.3 To agree to delegate to Executive Director for Climate, Environment and Customer to award the contract to the successful bidder following the procurement process.
Decision Criteria
This Decision does not contain any decision criteria records.
Divisions
This Decision does not contain any Division records.
Topics
This Decision does not contain any Topic records
Overview and Scrutiny
This Decision does not contain any Overview and Scrutiny records.
This section allows you to view the reports for the Decision.
This section displays the history of the Decision.
Decision History
| 24/07/2025 16:42:24 | Chloe O'Malley | Business Item Created | |
| 24/07/2025 16:43:27 | Chloe O'Malley | Report Added | Document ID 258324: FP-163-07-25 |
| 24/07/2025 16:43:44 | Chloe O'Malley | Status Changed | Decision Proposed [2] |
| 24/07/2025 16:43:56 | Chloe O'Malley | General Details Edited | |
| 24/07/2025 17:07:37 | Chloe O'Malley | General Details Edited | |
| 04/08/2025 12:46:36 | Maise Riley | General Details Edited | |
| 04/08/2025 12:47:44 | Maise Riley | General Details Edited | |
| 01/09/2025 17:45:28 | Maise Riley | General Details Edited | |
| 23/09/2025 16:54:52 | Maise Riley | General Details Edited | |
| 23/09/2025 17:00:54 | Maise Riley | Report Added | Document ID 262353: KD02 FP-163-07-25 Appendix 1 ECIA |